North/South line running tunnel city centre

For the running tunnels, a twin bored tunnel is applied that follows the street pattern as closely as possible and is lowered to a great depth to minimise the construction effects (since high water tables and soft soils had to be dealt with).
inside of the nord-south metro line in Amsterdam

Project description

The total length of the bored tunnel part is approx. 3.2 km; the outer diameter is approx. 7 m. Since the streets are very narrow the tunnels are bored with only 0,5 x diameter clearance. On some sections in the South the tunnels even had to be bored above each other because positioning the tunnels next to each other was not possible.  

It is obvious that the assessment of possible construction risks in this urban environment is of high importance. Therefore, a combination of the principles of 3D value engineering and design by testing is adopted. 3D value engineering is used to optimise the design by means of parametric studies thereby applying advanced 4D FE models to predict the impact due to tunnelling and for which the advanced tunnel boring machine (TBM) is considered. Since the interaction between the ground and structure plays an important role, the FE models are not always considered to be reliable up to the level that is required. In these cases, full scale tests are carried out for verification reasons meaning that the design is confirmed by way of testing. Furthermore, advanced TBM techniques are developed to limit damage to historic buildings. It includes:

  • a compact shield system (Vario) that can be adjusted during boring depending on the varying ground conditions
  • a TBM process control system that will be supported by means of the GIS Settlement Risk Management tool
  • an innovative concept of the tail of the TBM with an injection principle that was tested on a scale of 1:5. The tests proved that assessment of the settlements improved significantly. 

This information was provided to the contractor during the tender phase. The selected contractor decided to implement all techniques in the TBM that eventually was used.
On a number of locations, along the metro line, there was support available to several buildings by means of the compensational grouting technique, while the TBM was passing.

The lining design consists of 0.35 m thick segments and includes a special joint design that is accommodating an optimised structural interaction between the ring sections.

 

Scope of work

The consultancy services included:

  • Feasibility study in which a single large diameter bored tunnel was compared against twin smaller diameter bored tunnels in terms of costs and impact on the historic structures
  • Pre-design, final design, tender design and detailed design
  • Tender documentation and consultation
  • Contract management and supervision

Project facts North/South line running tunnel city centre

  • Client
    Municipality of Amsterdam
  • Project duration
    1994-2012
  • Country
    Netherlands
  • Project phase
    All project phases
  • Location 
    Amsterdam 
Frank Kaalberg - Senior Expert Tunneling and Deep Excavations

FrankKaalberg

Senior Expert Tunneling and Deep Excavations