Project description
The mechanical and electrical installations renovation for the Drechttunnel comprise:
- Energy power systems
- Distribution systems
- UPS-system
- Plant control and control systems
Scope of work
To prepare a conceptual design, a final design and tender documents. Control of detailed engineering and construction of the installations. Responsible for construction supervision management on site.
Specification sheet
2 page(s) - 266 kB
Client
Ministry of Transport and Public Works
In co-operation with
Not applicable
Type of project
Country
The Netherlands
Location
Rotterdam
Project duration
1999 - 2004
Project phase
Completed
Construction cost
€ 2.700.000,= (excl. VAT)
Consultancy fee
Design and tender documents € 105.000,= ; Construction and testing phase € 360.000,= (excl. VAT)